Monday, September 21, 2020

274 S. Matanzas Blvd- Railed Board Check

Avoiding problems is wise, but most of the time builders fail to be proactive and end up reacting to too many problems that could have been avoided had they taken the time to plan and think ahead. 

Today I'm measuring the railed form boards to double check they were installed per-plan dimensions for the mono slab. If this is out a few inches, it creates huge problems because the floor joists are built per-plan, and they will fall short of the top plate framed wall if the slab is over poured. Think it doesn't happen for real? More than you can imagine, unfortunately. 



Tuesday, September 15, 2020

274 S. Matanzas Blvd Soil Compaction

 I get asked about the process for ensuring new fill is ready for building. Watch this video to learn more about the process. 




274 S. Matanzas Blvd Fill


 

Wednesday, September 9, 2020

274 S. MATANZAS BLVD START

Getting ready to start a new home for client on a great corner lot in St Augustine. Stay tuned for more info.