Monday, October 19, 2020

274 S Matanzas Blvd Trusses Set Today

2nd floor exterior walls done and ready for the crane to set the roof trusses. 




Saturday, October 17, 2020

274 S Matanzas Blvd Framing Starts

Foundation work is finished. Now the framers are on-site today working hard. We've set an ambitious goal to be done in 6 days. Stay tuned to see the next post after we're dried in and ready for roof shingles.