Sheathing now complete. Plumbing and HVAC subs start tomorrow. Video tour of this custom home below.
List of current and past blog posts (see Blog Archive). Scroll slider to see more recent Blog postings
Wednesday, December 26, 2018
Wednesday, December 19, 2018
Monday, December 17, 2018
898 Ponte Vedra Blvd Roof Sheathing
Getting close to being dried in, which means other trades will be starting their work very soon, e.g. plumber, HVAC, electrical....
Wednesday, December 5, 2018
Wednesday, November 7, 2018
213 Oglethorpe Blvd Finished
One of my favorite lots at Davis Shore off Oglethorpe Blvd is done and closes today. Homeowner likes pink, so we tailored this door color for Jennifer.
Friday, November 2, 2018
Monday, October 29, 2018
Friday, October 26, 2018
213 Oglethorpe Blvd Landscaping
At the final stage for this new home. Landscaping looks great and sod excellent muck base quality. Final pics and video coming soon.
Wednesday, October 24, 2018
898 Ponte Vedra Blvd Framing Start
Exciting to see the framing work begin today. This phase is projected to take 6 six weeks to complete.
Wednesday, October 17, 2018
898 Ponte Vedra Blvd Slab Ready
After six month of sur-charging 268 loads of fill, this slab is ready to be poured in the morning. Framing crew onsite soon and this project will go vertical. I look forward to seeing this home stand its own from a design standpoint among many premier homes on the boulevard.
Sunday, July 15, 2018
Monday, June 18, 2018
15 Miruela Ave Finished
The Kline Family gets to move into their new home....what a pleasure to work for such a wonderful client.
Friday, June 8, 2018
Thursday, May 17, 2018
Wednesday, May 9, 2018
119 Arredondo Ave
Under contract now. Only one lot left in Davis Shores for our last new construction home in this hot neighborhood.